Humboldt Avenue improvements

County Road 57 in Minneapolis

Hennepin County, in partnership with the Minnesota Department of Transportation and the city of Minneapolis, will be reconstructing a multitrack railroad crossing north of Memorial Parkway to improve safety and efficiency.

Expand all information

Project information

Construction started August 13

On August 13, crews closed Humboldt Avenue (County Road 57) just north of Memorial Drive for reconstruction. Weather permitting, Humboldt Avenue reconstruction will be complete by early October 2018.

Detour information

No through traffic will be allowed during the full closure. People driving should use the signed detour: 

  • Humboldt Avenue
  • Shingle Creek Drive
  • 45th Avenue North
  • 44th Avenue North

Pedestrian detour

Access for people walking will be maintained during this closure. People walking should use the signed detour:

  • Humboldt Avenue
  • Shingle Creek Drive
  • 45th Avenue North
  • south Grand Rounds Trail

Bicycle detour

North Grand Rounds Trail will be closed during construction. Bicyclists should follow the south Grand Rounds Trail at 45th Avenue North. 

About this project

This railroad crossing is unique in that it has four separate at-grade rail crossings at a skewed angle to the roadway.

Federal and State Aid funds have been allocated for the design and construction of the following elements to improve safety and level of service:

  • Upgraded signal equipment and crossing gates
  • Raised roadway medians to prevent illegal vehicle maneuvers
  • Improved lighting and pedestrian facilities near the tracks

Public involvement

Construction

Hennepin County and the City of Minneapolis invite you to learn more about an upcoming project on Humboldt Avenue at the railroad intersection north of Memorial Drive. 

Construction open house

Monday, August 13, 2018
6 p.m. to 8 p.m.

Webber Community Center 
4401 Bryant Avenue North
Minneapolis, MN 55412

Project staff will be on hand to provide a project overview - including anticipated project layouts and tentative construction timeline. This is an opportunity to meet with project staff and ask any questions you might have about the project.

Design

Hennepin County, in partnership with the Minnesota Department of Transportation and the City of Minneapolis, hosted an open house in December 2017 for the reconstruction of Humboldt Avenue (County Road 57) at the railroad intersection. Construction is anticipated to begin in summer 2018.

Updated project layout (PDF)

Collapse all information