Washington Avenue (County Road 152)

Between Hennepin Avenue and Fifth Avenue South

Hennepin County, in coordination with the City of Minneapolis, is reconstructing Washington Avenue South (County Road 152) between Hennepin Avenue and Fifth Avenue South.

Utility relocation work began early in 2016. County crews will begin reconstruction work in August 2016. The project is scheduled to be complete in 2017.

Expand all information

Detours and road closings

Marquette Avenue South work

Crews will be working in the northwest corner of the intersection of Washington Avenue and Marquette Avenue starting Wednesday, August 24. All northbound traffic on Marquette will be detoured onto Washington Avenue, Third Avenue South and First Street. The closure is expected to last one week (schedules are subject to change). Buses traveling southbound on Marquette will be unaffected by the closure.

 

Washington Avenue detour 

Starting early morning on Monday, August 15, the detour of westbound lanes of Washington Avenue (County Road 152) in downtown Minneapolis will begin at Portland Avenue. The detour currently begins at Second Avenue South. 

 

This detour for motorists and bicyclists will follow Portland Avenue, Third Street South, Hennepin Avenue and then return to Washington Avenue. There is no detour for pedestrians or eastbound Washington Avenue. 

 

In addition, eastbound traffic will be reduced to two lanes through the work area. 

 

Construction schedule

Starting in spring 2016 and prior to the reconstruction, utility crews will be working in the area to relocate utilities.

County crews will follow behind the utility crews to begin the county’s reconstruction efforts. The reconstruction schedule is as follows:

2016

  • Summer/Fall: Start work on westbound lanes

2017

  • Spring: Complete work on westbound lanes  
  • Summer/Fall: Complete work on eastbound lanes

Anticipated construction staging plan (PDF)

Learn more

This section of Washington Avenue is part of County Road 152, which goes from Highway 62 in Minneapolis to County Road 81 in Brooklyn Park. County Road 152 is a turnback from the Minnesota Department of Transportation, who managed it when it was State Highway 52. The turnback status provides state money for completion of this project.  

When complete, the project will:

  • Add dedicated turn lanes at key intersections
  • Provide more space for pedestrians and shorten crossing distances at intersections
  • Provide one-way cycle tracks, or protected bike lanes

The project received approval of the preliminary layout from the Minneapolis City Council in 2014.

Preliminary layout 3 - January 2014 (PDF 6MB)

Washington Avenue corridor

Although construction will end at Fifth Avenue South, the design was created to include the rest of Washington Avenue to I-35W. The concept plans will provide guidance as future projects are identified and as funding becomes available. 

Draft traffic operation analysis - April 2013 (PDF 9MB)

Existing conditions layout - May 2013 (PDF)

Land use context and typology - May 2013 (PDF 5MB)

Area wide plan - May 2013 (PDF 7MB)

Public involvement

Construction

A pre-construction open house was held in August 2016. 

Design 

A public meeting was held December 4, 2012. Attendees provided input on existing conditions, challenges, opportunities and preliminary alternatives.

Public involvement part 1 summary report (PDF 18MB) 

A second public meeting was held May 14, 2013 to gain public input on concept layout alternatives and urban design elements. Input was also gathered through online surveys and stakeholder meetings.

Public involvement part 2 summary report - July 2013 (PDF 12MB)

There was strong public feedback supporting a bicycle lane behind the curb to make it more accessible for bicyclists. Following these sessions, the staff developed Preliminary Layout 3.

Collapse all information
Top