Minnehaha Avenue (County Road 48)

Hennepin County, in partnership with the City of Minneapolis, is reconstructing Minnehaha Avenue from 46th Street South to Lake Street.

Improvements to Minnehaha Avenue are needed to address the deteriorating pavement, utility and drainage concerns, non-motorized accommodations and storm water quality conditions. The county seeks to design Minnehaha Avenue to be safer, more livable, and welcoming to all users, while balancing potential impacts to residents and businesses along the corridor.

Expand all information

Detours and closures

Minnehaha Avenue closure between 38th and 34th streets begins October 3

Minnehaha Avenue will be closed between 38th and 34th streets beginning at 6 a.m. on Monday, October 3 to begin the final layer of asphalt paving. The 38th Street intersection will remain open to traffic, but the intersections at 37th, 36th, 35th, and 34th streets will close for a few hours at a time when crews are paving through the area. Adjacent intersections will not be closed at the same time. 

To allow space for crews and to ensure a successful finished product, parking will also be restricted. Please note any advance 'No Parking' signs in the area and move vehicles before the work begins to avoid being towed.

Lane Closure on Lake Street begins September 26

The eastbound lanes on Lake Street between Snelling and 27th avenues will remain shifted to the north while crews install concrete curbs and sidewalks at the south side of the Lake Street/Minnehaha Avenue intersection. These lane closures are anticipated to remain in place until mid-October.

Two lanes in each direction on Lake Street remain open, but the left-turn only lanes at the intersection are temporarily closed. The left lane in each direction will function as both a left turn and through lane (see map below).

Lane shifts map (png 17 kb)

Please expect delays and allow for some extra time if you are driving through the area. 

Southbound-only traffic changes between Lake Street and 27th Avenue

Traffic on Minnehaha Avenue is one lane, southbound only between Lake Street and 27th Avenue while Minnehaha Avenue project crews reconstruct the west side of the road (including storm sewer work, soil replacement, and curb installation). Work in the area and the southbound-only restrictions will continue into mid-September.

Minnehaha Avenue closed between 34th and Lake streets

Minnehaha Avenue is closed to through traffic between 34th and Lake streets and reopened between 38th and 34th streets. Posted detours will direct through traffic around the construction area using Lake Street, Hiawatha Avenue and 42nd Street. Access to local residents and businesses will remain available. The road is anticipated to remain closed to through traffic until approximately November 2016.

2016 closures and detours

Minnehaha Avenue is closed and being reconstructed in two main stages in 2016:

  • April-August: 38th to 34th Street
  • August-November: 34th to Lake Street

Detour maps

Local traffic

Local traffic will be able to use fully paved streets and walkways in all areas except the four blocks under construction. Access to businesses and residences will remain available in the four block segment under construction, though surfaces may not be paved or smooth at all times.

Crossing Minnehaha Avenue

Travelers will be able to cross Minnehaha Avenue at intersections not closed for reconstruction during construction. With the exception of Lake Street, intersections will be fully closed for approximately ten days to allow for construction in and/or around the intersection. Travelers may cross at other locations during these intersection closures.

Metro Transit

During construction, Metro Transit will detour bus routes around Minnehaha Avenue as needed. Visit Metro Transit's riders alert page to get updated on particular routes in the area.

Construction updates

Crews are working between 34th and Lake streets. Crews are beginning asphalt paving and prepping for sod installation between 34th and 32nd streets, and completing paving between 32nd and Lake streets.

Other projects on Minnehaha Avenue

City construction on 38th Street, west of MInnehaha Avenue is progressing and the street is expected to open to traffic September 23 or early the following week. Additional information on the project can be found on the City of Minneapolis website.

Construction notice - Summer 2016 (PDF)

Project background

Design concepts

The county initially studied design concepts for buffered bike lanes, one-way cycle track and two-way cycle tracks on Minnehaha Avenue. County staff recommended the buffered bike lane option because it better addresses safety at intersections for pedestrians, bicyclists and vehicles and will have less of an impact on parking and trees. Minneapolis City Council approved the recommended layout on December 13, 2013.

Project documents

Preliminary layout (PDF)

Visualizations (PDF)

Proposed utility work and excavation limits (PDF)

Public involvement

Public meetings were held in 2013 to provide information about design concepts and gain public input. Hennepin County presented the recommended layout to Minneapolis City Council in December 2013 and received preliminary layout approval.

Thank you to all who have attended meetings and provided your thoughts and ideas to date.

Project highlights

  • Two 11-foot lanes of traffic
  • Dedicated left turn lanes on Minnehaha Avenue at 31st Street, 32nd street, 38th Street, 46th Street
  • A southbound right turn lane on Minnehaha Avenue at 42nd Street
  • Realignment of intersections to create 90 degree angles at 27th Avenue and 31st Avenue, 32nd Street and 33rd Street, and 36th Avenue and 37th Avenue
  • Improved pedestrian facilities (shortened crossings at intersections, improving bus stops and ramp curbs to make them fully accessible)
  • Enhanced dedicated bicycle lanes (including a stipend buffer zone and concrete pavement treatment)
  • Storm water system improvements 

Utility improvements

CenterPoint Energy will continue improving the gas mains in this corridor in 2016 between 32nd Street and 22nd Avenue. Visit Centerpoint Energy's project website for more information.

Residents may improve their sewer and water service lines when the street is being reconstructed. For questions regarding water and sewer service replacement, contact 612-930-4211 or minnehaha@hennepin.us.

Collapse all information
Top