We’re working to minimize impacts during construction.
September 15-19
Project crews will repave and restripe Hennepin Avenue and Stinson Boulevard.
- East Hennepin Avenue, as well as Stinson Boulevard, will be reduced to a single lane in each direction. Flaggers will guide traffic at intersections.
- Cross streets and business access will remain open, but there may be short delays as paving crews proceed through the project area.
- Be alert for crews and drive slowly. Allow extra travel time or consider an alternative route.
We'll install temporary lane striping after paving is complete. In October, crews will return to install the final lane markings. That work will require about two days of short-term, single lane closures.