Minnehaha Avenue (County Road 48)

Hennepin County, in partnership with the City of Minneapolis, is reconstructing Minnehaha Avenue from 46th Street South to Lake Street.

Improvements to Minnehaha Avenue are needed to address the deteriorating pavement, utility and drainage concerns, non-motorized accommodations and storm water quality conditions. The county seeks to design Minnehaha Avenue to be safer, more livable, and welcoming to all users, while balancing potential impacts to residents and businesses along the corridor.

Project information pop up meeting

Gandhi Mahal Restaurant
3009 27th Avenue South - Community Room
Wednesday, August 24
2:00 p.m. - 5:00 p.m.

There is no formal presentation, so stop by at any time!

Expand all information

Detours and closures

Southbound-only traffic changes between Lake Street and 27th Avenue

Traffic on Minnehaha Avenue is one lane, southbound only between Lake Street and 27th Avenue while Minnehaha Avenue project crews reconstruct the east side of the road (including storm sewer work, soil replacement, and curb installation). (see map (PDF)). Work in the area and the southbound-only restrictions will continue into mid-September.

Minnehaha Avenue/32nd Street intersection reopens August 26

Minnehaha Avenue project crews are completing the reconstruction of the 32nd Street intersection and anticipate it will reopen to traffic by the end of day Friday, August 26. This intersection will reopen to a gravel surface until asphalt paving occurs later this fall.

Minnehaha Avenue closed between 34th and Lake streets

Minnehaha Avenue is closed to through traffic between 34th and Lake streets and reopened between 38th and 34th streets. Posted detours will direct through traffic around the construction area using Lake Street, Hiawatha Avenue and 42nd Street. Access to local residents and businesses will remain available. The road is anticipated to remain closed to through traffic until approximately November 2016.

2016 closures and detours

Minnehaha Avenue is closed and being reconstructed in two main stages in 2016:

  • April-August: 38th to 34th Street
  • August-November: 34th to Lake Street

Detour maps

Local traffic

Local traffic will be able to use fully paved streets and walkways in all areas except the four blocks under construction. Access to businesses and residences will remain available in the four block segment under construction, though surfaces may not be paved or smooth at all times.

Crossing Minnehaha Avenue

Travelers will be able to cross Minnehaha Avenue at intersections not closed for reconstruction during construction. With the exception of Lake Street, intersections will be fully closed for approximately ten days to allow for construction in and/or around the intersection. Travelers may cross at other locations during these intersection closures.

Metro Transit

During construction, Metro Transit will detour bus routes around Minnehaha Avenue as needed. Visit Metro Transit's riders alert page to get updated on particular routes in the area.

Construction updates

Crews are working between 34th and Lake streets. Crews continue removing pavement and replacing soils and structures beneath the road. Concrete driveway apron and shoulder paving has begun between 34th and 32nd streets and may require work that goes into the evening. Sign up for night work email or text updates or call the hotline at 612-390-4211 and press 1 for recorded night work information. 

The 38th and 35th street intersections will continue operating under 4-way stop conditions until the permanent signal cabinets are installed this fall.

Other projects on Minnehaha Avenue

CenterPoint Energy crews are completing work on their gas lines and services on Minnehaha Avenue between 31st and Lake streets. CenterPoint Energy will be working north of Lake Street  the week of August 22.

Please visit CenterPoint Energy's website for project contacts, anticipated schedule, traffic impact information and to sign up for project updates.

The city of Minneapolis has begun construction on 38th Street, west of Minnehaha Avenue. More information can be found on the City of Minneapolis website.

Construction notice - Summer 2016 (PDF)

Project background

Design concepts

The county initially studied design concepts for buffered bike lanes, one-way cycle track and two-way cycle tracks on Minnehaha Avenue. County staff recommended the buffered bike lane option because it better addresses safety at intersections for pedestrians, bicyclists and vehicles and will have less of an impact on parking and trees. Minneapolis City Council approved the recommended layout on December 13, 2013.

Project documents

Preliminary layout (PDF)

Visualizations (PDF)

Proposed utility work and excavation limits (PDF)

Public involvement

Public meetings were held in 2013 to provide information about design concepts and gain public input. Hennepin County presented the recommended layout to Minneapolis City Council in December 2013 and received preliminary layout approval.

Thank you to all who have attended meetings and provided your thoughts and ideas to date.

Project highlights

  • Two 11-foot lanes of traffic
  • Dedicated left turn lanes on Minnehaha Avenue at 31st Street, 32nd street, 38th Street, 46th Street
  • A southbound right turn lane on Minnehaha Avenue at 42nd Street
  • Realignment of intersections to create 90 degree angles at 27th Avenue and 31st Avenue, 32nd Street and 33rd Street, and 36th Avenue and 37th Avenue
  • Improved pedestrian facilities (shortened crossings at intersections, improving bus stops and ramp curbs to make them fully accessible)
  • Enhanced dedicated bicycle lanes (including a stipend buffer zone and concrete pavement treatment)
  • Storm water system improvements 

Utility improvements

CenterPoint Energy will continue improving the gas mains in this corridor in 2016 between 32nd Street and 22nd Avenue. Visit Centerpoint Energy's project website for more information.

Residents may improve their sewer and water service lines when the street is being reconstructed. For questions regarding water and sewer service replacement, contact 612-930-4211 or minnehaha@hennepin.us.

Collapse all information
Top