Douglas Drive reconstruction

County Road 102 in Golden Valley 

Hennepin County, in partnership with the City of Golden Valley, is reconstructing Douglas Drive (County Road 102) from Highway 55 to Medicine Lake Road (County Road 70). County reconstruction work began in July 2016 and is scheduled to be complete November 2017.

Expand all information

Current work

Streetscape improvements continue

Streetscape improvements are nearing completion on last year’s reconstruction from Medicine Lake Road (County Road 70) to Duluth Street (County Road 66).

Crews have finished pouring sidewalks and medians, as well as installed new street light fixtures. Also, traffic signal system installations at the Douglas Drive intersections at Duluth Street and Medicine Lake Road are almost complete. The new system will feature accessible signals to accommodate pedestrians with disabilities

Beginning in mid-June, the City of Golden Valley will begin landscaping along Douglas Drive from Medicine Lake Road to Duluth Street.

Street light

New street lights along Douglas Drive from Duluth Street to Medicine Lake Road were installed as part of the City of Golden Valley's overall streetscape improvements.

All of Duluth Street to be open by mid-July

Eastbound lanes of Duluth Street are taking shape as crews made significant progress the past few weeks. They paved the first two layers of pavement, installed curbs and cutters, and place medians on eastbound lanes of Duluth Street from Douglas Drive to Adair Avenue.

The focus now turns to:

  • Paving trails, sidewalks and driveways
  • Paving the final roadway surface
  • Shaping top soil for sod placement
  • Painting pavement lines and markings

Driveway

Framework for new driveway entrances have been built along Duluth Street. Crews will begin pouring in driveways, as well as sidewalks and trails, before finalizing work by mid-July.

Underground utility work nearing completion

Douglas Drive has been a busy site between Duluth Street and Golden Valley Road over the past two months, as more than 5,000 feet of new watermain and storm sewer pipes were installed and connected to other pipes. And, private utility partners have been removing overhead service lines and placing them in the ground with new upgraded cables and lines.

Crews are finishing underground utility work and will shift their focus on rebuilding and grading this segment of Douglas Drive to ensure a sturdy foundation for the new roadway, trails and sidewalks. Rebuilding the roadway is anticipated to take around a month.

During that time, crews will place and maintain gravel surfaces on Douglas Drive from Olympia Street heading north to Duluth Street for local traffic use by mid-July.

Weather permitting, we expect to complete the entire segment with fully paved road surfaces by mid-August.

Utility work progresses on Golden Valley Road intersection

Currently, private utility companies are removing old, unused gas lines and are burying their service lines underground. The work is being completed prior to watermain and storm sewer work. This will help minimize delays and complete reconstruction of the area more efficiently. We anticipate private utility work to be complete by early July.

For the next couple of months, the work will be extensive. A new roundabout will be constructed at the Golden Valley Road intersection. Crews will also replace underground utilities for watermain and storm sewer to meet the latest environmental and health safety standards. New sidewalks and trails designed to better address community needs will be installed.

Weather permitting, we anticipate completing this section by the end of August.

Vacuum 

A Public utility crew member uses a vacuum excavator to break up soil to find underground utilities without damaging other buried utility lines.

Dust, noise and vibrations in the construction area

Crews will be using large construction equipment throughout construction, creating dust, noise and slight vibrations. Dust, noise and vibrations are a normal part of a construction project. The project team is working in accordance with noise ordinances set by the City of Golden Valley. The team also has a vibration control plan to make sure that vibrations stay within standard acceptable limits. Dust is being monitored and controlled in order to keep levels at a minimum.

If you have concerns or questions about noise and/or vibrations, please contact the project at 612-543-3485.

Closures and traffic access

Closure to through traffic

Douglas Drive (County Road 102) is closed to through traffic between Duluth Street (County Road 66) and Golden Valley Road. Access to this segment of roadway is for local traffic only and is anticipated to be completed in mid-August. The purpose of this closure is to reconstruct the roadway and complete various utility improvements along the corridor.

For everyone's safety, please use the detour if your destination is outside the work area. The detour follows Duluth Street, Highway 100, and Olson Memorial Highway (Highway 55).

Douglas Drive detour

Printable detour map (PDF)

Golden Valley Road to Frontage Road closed to through traffic

On Tuesday, June 13, Douglas Drive closed to through traffic from Golden Valley Road to just north of the Frontage Road as crews began reconstruction in the area.

The work will be extensive as crews will construct a new roundabout at the Golden Valley Road intersection. They will also replace underground utilities for water, storm sewer and sanitary sewer to meet the latest environmental and health safety standards.

When dirt is back in place, they will rebuild curbs and gutters. New sidewalks and trails designed to better address community needs will be finished. Then, blacktop pavement will be added.

Alternate routes and signage will be provided for the businesses in the industrial park via the Frontage Road. All through traffic are encouraged to use the detour route that includes Highway 55, Highway 100 and Duluth Street (County Road 66).

Please anticipate heavy construction work and full road closures in this area until the end of August.

Access for local traffic

The project team will be maintaining access for residents and businesses along the construction areas of Douglas Drive and Duluth Street. They will provide signed detours for any closures and rerouting that are needed. In general, the following are expected:

  • On Duluth Street, one lane in each direction will be provided for vehicle traffic during the majority of the work.
  • On Douglas Drive near St. Croix Avenue, a through lane will be provided for businesses. Entry signage will be posted along side streets for businesses residing on Douglas Drive.
  • For apartment complexes and condominiums along Douglas Drive, access to side streets will be provided for residents. Entry signage will be posted along side streets to guide residents. Please note that the entry signage can move on a daily basis depending on where crews are working.
  • At least one pedestrian access route will be maintained at all times, unless there are safety concerns.

It is important to follow the speed limits and signs, and stay alert in this area, including during evenings and weekends. Traffic changes, construction crews, equipment and work areas near the roadway will require extra attention from road users.

 

Work zone conditions

 

Please remember, throughout the work zone, we have removed pavement and are working with dirt. This means that roads will be more challenging to drive through. While we continue to try to keep things driveable, weather – especially heavy rains – can create challenges. We appreciate everyone’s patience and understanding. If you have questions or concerns regarding the road conditions, please contact the project at 612-543-3485.

 

Metro Transit during construction

 

As a result of the Douglas Drive reconstruction project, there are changes to Metro Transit bus stops and route detours.

 

The best way to stay updated on bus stop changes and route detours is to visit Metro Transit's rider alerts website at www.metrotransit.org/rider-alerts. Riders can also follow the instructions posted at the bus stops or contact the Metro Transit hotline at 612-373-3333.

 

Construction schedule

2017 schedule

Spring/Summer

  • Reconstruction of Duluth Street from Douglas Drive to Adair Avenue
  • Reconstruction of Douglas Drive from Duluth Street to Golden Valley Road. This includes a new signal system at Duluth Street and a new railroad crossing
  • Completion of pond work and culvert reconstruction, including reconstruction of box culvert between Phoenix Street and Golden Valley Road

Summer/Fall

  • Reconstruction of Douglas Drive from Golden Valley Road to Highway 55 Frontage Road. This includes a new roundabout at the Golden Valley Road intersection and a new signal system at the Highway 55 Frontage Road intersection

Fall

  • Reconstruction of Douglas Drive from Highway 55 Frontage Road to Highway 55. This includes a new signal system at the Highway 55 and Douglas Drive intersection, which will require temporary lane closings.

2017 staging plan

2017 construction stages

Download a printable version of this staging plan graphic here (PDF)

Learn more

The Douglas Drive corridor project will reconstruct nearly two miles of Douglas Drive between Olson Memorial Highway and Medicine Lake Road (County Road 70). This project will create a safer and more efficient road for all users by improving connectivity, traffic flow, pedestrian safety and aesthetics.

The 2016-17 reconstruction project will be done in partnership with the City of Golden Valley and will feature:

  • Additional turn lanes
  • Improved sidewalks
  • Redesigned intersections
  • Widened right-of-ways for shoulders and bike lanes
  • Relocated utilities
  • New streetlights and landscaping
  • New roundabouts at Sandburg Lane and Golden Valley Road.

What are the benefits of roundabouts?

Roundabouts offer many benefits over intersections controlled by traffic signals or stop signs, and are becoming more prevalent on Hennepin County roads and are growing in popularity.

Some of the ways that roundabouts offer benefits over controlled intersections are that it:

  • Lower traffic speeds
  • Improves traffic flow by promoting continuous flow of traffic
  • Shorter crosswalks for pedestrians and bicyclists
  • Increases safety as traffic moves in only one direction, virtually eliminating the possibility for t-bone and head-on collisions

While roundabouts may seem narrow to many drivers, the lane widths are designed to accommodate all types of vehicles including trucks, emergency vehicles, school buses and snow plows.

Why are the center island of roundabout being built up?

The main reason why modern roundabouts have a raised center island is primarily for safety. The raised island keeps the driver's focus on the left line of sight for vehicles, as well as cyclists and pedestrians, when driving into and through the roundabout. It also enhances a driver’s recognition of the upcoming roundabout and island.

More information on the history of the project can be found on the City of Golden Valley website.

Public involvement

Previous events

The City of Golden Valley, in partnership with Hennepin County, hosted an open house for the Douglas Drive reconstruction project on March 28, 2017. The open house focused on providing residents and businesses with information on the 2017 reconstruction from Duluth Street to Highway 55.

The City of Golden Valley, in partnership with Hennepin County, hosted an open house for the Douglas Drive reconstruction project on May 19, 2016. The open house focused on providing residents and businesses with information on the 2016 reconstruction from Medicine Lake Road to Duluth Street.

Related documents

General information about roundabouts (PDF)

Collapse all information
Top